Timeline is one of the top concerns Montreal homeowners have before starting a bathroom renovation. Nobody wants to be without a bathroom for weeks. Here is a realistic breakdown of how long different scopes of bathroom renovation actually take on the South Shore.
Short Answer: Bathroom Renovation Timelines
- Tub-to-shower conversion: 7 to 10 business days
- Full bathroom gut renovation: 10 to 16 business days
- Primary bathroom with expansion: 3 to 5 weeks
- Powder room renovation: 4 to 7 business days
These timelines assume proper planning, materials ordered and on-site before demo begins, and a dedicated crew. A contractor who is juggling multiple jobs simultaneously and sending one person every other day will take significantly longer.

Why Timelines Vary
Material Lead Times
The biggest timeline killer in a bathroom renovation is waiting for materials that were not ordered in advance. Tile, vanities, shower fixtures and glass enclosures all have lead times. If your contractor starts demo before materials are confirmed and on order, you may find your bathroom sitting open for weeks waiting for a vanity.
Before demo begins, every material should be selected, ordered and ideally on-site or confirmed with a delivery date. This is part of what a properly managed renovation looks like.
Hidden Issues
Old homes on the South Shore sometimes reveal surprises once the walls are open: outdated plumbing, inadequate waterproofing that failed years ago, subfloor damage from old leaks. These add time and cost. A good contractor will walk you through what they found and what it means for the timeline and budget before proceeding.
Scope of Plumbing Changes
If the toilet, shower drain or sink location stays where it is, plumbing work is minimal. If drains or supply lines need to move, expect to add 1 to 3 days for the plumbing rough-in, plus inspection time depending on your municipality.
Ready to Get a Real Number for Your Renovation?
We come to your home, walk the scope with you, and give you a detailed written estimate within a few days. No vague ranges, no pressure. Just an honest price from a team that delivers.
Book Your Free Consultation or call (438) 255-2501.
Week by Week: What a Bathroom Renovation Looks Like
Week 1
Demolition, removal of all existing fixtures, tile and drywall. Plumbing rough-in for any relocated fixtures. Electrical rough-in for new lighting or heated floor. Inspection if required. Subfloor repair and preparation. Waterproofing membrane installation.
Week 2
Tile installation on floor and walls. This is the most time-consuming phase because tile setting and grouting require curing time between stages. Niche installation. Cement board or backer substrate for tile areas. Shower pan and curb if applicable.
Week 3 (for Larger Scopes)
Glass enclosure installation (typically requires a separate trade with lead time). Vanity, toilet and fixture installation. Paint. Accessories and trim. Final electrical connections. Punch list and cleanup.

How to Avoid a Drawn-Out Renovation
- Have all materials selected and ordered before demo starts. This is the single most important step.
- Work with a contractor who has a dedicated crew for your project. A crew of one who shows up three days a week will take twice as long.
- Make decisions in advance. Changing tile selection mid-project restarts the material lead time clock.
- Confirm the full scope before signing. Discovering you also want to move the toilet location after demo has started adds time and cost.
What Freire Management Commits To
A standard full bathroom renovation takes us about two weeks of work, around 10 working days. We plan the materials before demo, keep a dedicated team on your project and give you an approximate schedule in writing after the visit, based on your bathroom. Nobody can promise an exact date before the walls are open, so if something changes, we tell you right away, not at the end.
We work across the South Shore including Candiac, La Prairie, Saint-Lambert, Greenfield Park, Chambly and Saint-Bruno.